1Shift Information
Company Date Shift System
SAFARI November 22, 2026 Shift A 7 AM – 3PM Airport Electrical System
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
10:00 Maintenance Power Gen Testing Assistance Reference
12:10
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
123456 None None Electrical lead  November 23, 2026 Closed
5Shift Remarks
Shift Remarks

No Major Activites

1Shift Information
Company Date Shift System
SAFARI November 22, 2026 Day Shift (A) 6 AM – 6 PM Airport Mechanical System
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
00:00 Inspection Na Na
15:19
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
NA NA Na Mechanical Lead Closed
5Shift Remarks
Shift Remarks

No major activities has been conducted for the reported date.

1Shift Information
Company Date Shift System
SAFARI November 22, 2026 Shift B 3 PM – 11 PM Airport Electrical System
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
20:00 Maintenance NA NA
17:40
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
NA NA NA Electrical lead  Closed
5Shift Remarks
Shift Remarks

No Major activities

1Shift Information
Company Date Shift System
SAFARI November 22, 2026 Shift B 3 PM – 11 PM
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
17:49 Inspection //////////// //////////
17:49
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
2278, 53405 ctix 4,5 are off due to water leakage, XCT-4 is upgrade for scatter kit water drain, still working on it Shift Lead, Shift Lead November 22, 2026 Open, Open
5Shift Remarks
Shift Remarks

all machine working normally just Ctix 4-5 & Xct-4 are out of services

1Shift Information
Company Date Shift System
SAFARI November 23, 2026 Shift C 11 PM – 7 AM Aerodrome Maintenance
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
21:43 Inspection ////////// /////////////
21:43
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
2278, 53405 ctix 4,5 are off due to water leakage, XCT-4 is upgrade for scatter kit wait water drain, still working on it Shift Lead, Shift Lead November 22, 2026 Open, Open
5Shift Remarks
Shift Remarks

all machine working normally just Ctix 4-5 & Xct-4 are out of services

1Shift Information
Company Date Shift System
SAFARI November 23, 2026 Shift C 11 PM – 7 AM
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
07:00 Inspection None None
02:57
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
None None None Electrical lead  Closed
5Shift Remarks
Shift Remarks

All system operations are normal

1Shift Information
Company Date Shift System
SAFARI November 23, 2026 Shift A 7 AM – 3PM Airport Electrical System
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
11:29 Maintenance none 0
12:03
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
0 none none Electrical lead  November 24, 2026 Closed
5Shift Remarks
Shift Remarks

No major activity.

1Shift Information
Company Date Shift System
SAFARI November 23, 2026 Day Shift (A) 6 AM – 6 PM Airport Mechanical System
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
18:00 Inspection NA NA
14:52
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
NA NA NA Mechanical Lead Closed
5Shift Remarks
Shift Remarks

There is no major activity has been conducted for the reported date.

1Shift Information
Company Date Shift System
SAFARI November 23, 2026 Shift A 7 AM – 3PM Aerodrome Maintenance
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
13:10 Inspection All PBBs, GPUs & VDGS Daily Inspection N/A
07:15 Maintenance PBB Gate 27B/PM Schedule monthly PM
15:43
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
2434 Remove/Replace PBB vinyl flooring Remove/Replace PBB vinyl flooring Overall Shift Lead November 26, 2026 In Progress
5Shift Remarks
Shift Remarks

All equipment’s are working normally

1Shift Information
Company Date Shift System
SAFARI November 23, 2026 Shift B 3 PM – 11 PM Maintenance Common Services
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
19:46 Inspection ////////// /////////////
19:46
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
2278, 53405 ctix 4,5 are off due to water leakage, XCT-4 is upgrade for scatter kit Drying the machines, Activity Done Shift Lead, Shift Lead November 23, 2026, November 23, 2026 Open, Closed
5Shift Remarks
Shift Remarks

all machines working normally

1Shift Information
Company Date Shift System
SAFARI November 23, 2026 Shift B 3 PM – 11 PM Airport Electrical System
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
19:56 Inspection None None
19:56
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
None None None Electrical lead  Closed
5Shift Remarks
Shift Remarks

No Major activities.

1Shift Information
Company Date Shift System
SAFARI November 23, 2026 Shift B 3 PM – 11 PM Aerodrome Maintenance
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
16:00 Inspection N/A N/A
20:21
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
2434 Remove/Replace PBB vinyl flooring Remove/Replace PBB vinyl flooring Overall Shift Lead November 26, 2026 In Progress
5Shift Remarks
Shift Remarks

All equipment’s are working normally
No major activities

1Shift Information
Company Date Shift System
SAFARI November 24, 2026 Night Shift (B) 6 PM – 6 AM Maintenance Common Services
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
21:31 Inspection ////////// /////////////
21:31
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
2278 ctix 4,5 are off due to water leakage Drying the machines Mechanical Lead November 24, 2026 Open
5Shift Remarks
Shift Remarks

this is the shift remarks

1Shift Information
Company Date Shift System
SAFARI November 23, 2026 Night Shift (B) 6 PM – 6 AM Airport Mechanical System
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
03:02 Maintenance REPLACEMENT OF 8EA SMOKE DETECTORS AT M-LVL FIRE ALARM SYSTEM
23:22 Maintenance REPLACEMENT OF 9EA SMOKE DETECTORS AT I-LVL NEAR PASSENGER ENTRANCE FIRE ALARM SYSTEM
02:15
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
N/A Smok Detector Replacment Mechanical Lead Closed
5Shift Remarks
Shift Remarks

Job completed for replacing smok detectors for both Notification: 1000002489 and 1000002532
By FIRE ALARM SYSTEM team

1Shift Information
Company Date Shift System
SAFARI November 24, 2026 Shift C 11 PM – 7 AM Airport Electrical System
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
04:02 Inspection None None
04:02
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
None None None Electrical lead  Open
5Shift Remarks
Shift Remarks

All systems working normal

1Shift Information
Company Date Shift System
SAFARI November 24, 2026 Shift C 11 PM – 7 AM Aerodrome Maintenance
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
07:15 Maintenance GATE 16A – PBB, GPU & VDGS MONTHLY PM Schedule Monthly PM
04:17
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
2434 Remove/Replace PBB vinyl flooring Remove/Replace PBB vinyl flooring Overall Shift Lead November 26, 2026 In Progress
5Shift Remarks
Shift Remarks

Monthly pm in progress

1Shift Information
Company Date Shift System
SATCO November 24, 2026 Shift A 7 AM – 3PM Aerodrome Maintenance
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
12:00 Maintenance GATE 16A – PBB, GPU & VDGS Schedule Monthly PM/Completed
13:00 Inspection ALL PBBs, GPUs & VDGS Daily inspection/Completed
10:53
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
2434 Remove/Replace PBB vinyl flooring Remove/Replace PBB vinyl flooring Overall Shift Lead November 26, 2026 In Progress
5Shift Remarks
Shift Remarks

All Equipment’s are working normally.

1Shift Information
Company Date Shift System
STATION 1 November 24, 2026 Shift A 7 AM – 3PM Station 1
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
15:00 Maintenance No major activity N/A
12:08
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
N/A N/A N/A Station 1 Closed
5Shift Remarks
Shift Remarks

NO MAJOR ACTIVITY

1Shift Information
Company Date Shift System
METCO November 24, 2026 Shift A 7 AM – 3PM Maintenance Common Services
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
09:37 Maintenance the machine was out of service due to baggage stuck in the tunnel. Action: removed stuck bag and restarted device after that back to normal. 2540
12:54
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
2549, 53525 International departure ionscan is out of service., Power outage on the matrix server room but the system is working normally on UPS changing spare parts., is to work on the electricity. Shift Lead, Electrical lead  In Progress, Open
5Shift Remarks
Shift Remarks

Morning shift–Handover Report

*⚙️ Total
Number of Machines Out of Service*: CTiX 4 and 5
WTMD 2 , 3 HHMD, Bruker, Ionscan

✅ Status: Turned off due to the water leakage, ionscan is in progress.

📌 Notes: ✍️: All machines are working normally. Except the mentioned machines.

1Shift Information
Company Date Shift System
SAFARI November 24, 2026 Day Shift (A) 6 AM – 6 PM Airport Mechanical System
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
19:00 Inspection NA NA
15:03
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
NA NA NA Mechanical Lead Closed
5Shift Remarks
Shift Remarks

The systems were operating normally, and no major activities were carried out during the reported date and time.

1Shift Information
Company Date Shift System
METCO November 25, 2026 Night Shift (B) 6 PM – 6 AM Maintenance Common Services
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
21:39 Inspection ////////// /////////////
21:39
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
53525, 2549 Power outage on the matrix server room but the system is working normally on, International departure ionscan is out of service Electrical lead, changing spare parts Electrical lead , Shift Lead November 24, 2026 Open, Closed
5Shift Remarks
Shift Remarks

All machines working normally just CTIX 4&5

1Shift Information
Company Date Shift System
SAFARI November 24, 2026 Night Shift (B) 6 PM – 6 AM Airport Mechanical System
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
07:00 Maintenance N/A N/A
03:55
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
N/A N/A N/A Mechanical Lead November 25, 2026 Closed
5Shift Remarks
Shift Remarks

Normal

1Shift Information
Company Date Shift System
SAFARI November 25, 2026 Shift C 11 PM – 7 AM Airport Electrical System
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
04:19 Inspection None None
04:19
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
None None None Electrical lead  Closed
5Shift Remarks
Shift Remarks

System working Norma

1Shift Information
Company Date Shift System
STATION 1 November 24, 2026 Shift C 11 PM – 7 AM Station 1
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
07:00 Maintenance NO MAJOR ACTIVITY REPORTED N/A
03:44
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
N/A N/A N/A Station 1 Closed
5Shift Remarks
Shift Remarks

NO MAJOR ACTIVITY REPORTED

1Shift Information
Company Date Shift System
SATCO November 25, 2026 Shift C 11 PM – 7 AM Aerodrome Maintenance
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
06:00 Maintenance VDGS NR29 VDGS WEEKLY PM
04:46
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
2434 Remove/Replace PBB vinyl flooring Remove/Replace PBB vinyl flooring Overall Shift Lead November 26, 2026 Open
5Shift Remarks
Shift Remarks

All equipment working normal

1Shift Information
Company Date Shift System
SATCO November 25, 2026 Shift A 7 AM – 3PM Aerodrome Maintenance
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
12:42 Maintenance GATE 16B – PBB & GPU, MONTHLY PM Schedule Monthly PM
13:40 Inspection ALL PBB, GPU & VDGS inspection Daily inspection
11:09
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
2434, 2463 Gate 23&22 – Remove/Replace PBB vinyl flooring, Gate 16A – Replace PBB Tire Gate 23&22 – Remove/Replace PBB vinyl flooring, Gate 16A – Replace PBB Tire Overall Shift Lead, Overall Shift Lead November 26, 2026, November 25, 2026 In Progress, In Progress
5Shift Remarks
Shift Remarks

All equipment’s are working normally

1Shift Information
Company Date Shift System
STATION 1 November 25, 2026 Shift A 7 AM – 3PM Station 1
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
15:00 Maintenance No major activity N/A
11:59
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
N/A N/A N/A Station 1 Closed
5Shift Remarks
Shift Remarks

NO MAJOR ACTIVITY

1Shift Information
Company Date Shift System
STATION 1 November 25, 2026 Shift C 11 PM – 7 AM Station 1
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
23:00 Maintenance N/A N/A
12:19
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
N/A N/A N/A Station 1 Closed
5Shift Remarks
Shift Remarks

NO MAJOR ACTITY

1Shift Information
Company Date Shift System
METCO November 25, 2026 Shift B 3 PM – 11 PM Aerodrome Maintenance
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
00:01 Inspection //// ///////
13:14
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
2278, 2562 ctix 4,5 are off due to water leakage, ctix 7 out of service Drying the machines, still working on it Shift Lead, Shift Lead Open, Open
5Shift Remarks
Shift Remarks

all machine working normal expect ctix 4,5,7

1Shift Information
Company Date Shift System
SAFARI November 25, 2026 Day Shift (A) 6 AM – 6 PM Airport Mechanical System
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
12:00 Maintenance Major activity: Replacement of the damaged fire hydrant at the Main Fire Station was carried out. 1000002416
13:46
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
NA NA NA Mechanical Lead Closed
5Shift Remarks
Shift Remarks

Major activity: Replacement of the damaged fire hydrant at the Main Fire Station was carried out. (1000002416)

The systems were operating normally

1Shift Information
Company Date Shift System
SAFARI November 25, 2026 Shift B 3 PM – 11 PM Airport Terminals & Facilities
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
15:30 Maintenance installation office furniture at admin building 53637
15:00 Inspection Inspection below corrugated ceiling due to flood test part 3,4 mezzanin level Mezzanin Level inspection
19:26
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
Mezzanin Level inspection Inspection due to flood test Inspection below corrugated ceiling due to flood test part 3,4 mezzanin level Facility & Roads Lead November 26, 2026 In Progress
5Shift Remarks
Shift Remarks

The terminal condition is normal, with no abnormalities observed.

1Shift Information
Company Date Shift System
STATION 1 November 25, 2026 Shift B 3 PM – 11 PM Station 1
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
23:00 Maintenance NO MAJOR ACTIVITY REPORTED N/A
19:32
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
N/A N/A N/A Station 1 Closed
5Shift Remarks
Shift Remarks

NO MAJOR ACTIVITY REPORTED

1Shift Information
Company Date Shift System
SAFARI November 25, 2026 Shift B 3 PM – 11 PM Airport Electrical System
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
06:00 Maintenance Power energization of SWG-25 successfully completed, power restored to normal operation. none
19:52
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
NA Monitor work execution of ESB-105 project Monitoring work execution and ongoing site activities. Electrical lead  November 26, 2026 In Progress
5Shift Remarks
Shift Remarks

All System working in normal operation.

1Shift Information
Company Date Shift System
SAFARI November 24, 2026 Shift A 7 AM – 3PM Airport Electrical System
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
07:49 Maintenance none 0
20:32
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
0 None None Electrical lead  November 26, 2026 Closed
5Shift Remarks
Shift Remarks

No Major activity.

1Shift Information
Company Date Shift System
SAFARI November 25, 2026 Shift A 7 AM – 3PM Airport Electrical System
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
11:00 Maintenance none 0
20:33
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
0 None None Electrical lead  November 26, 2026 Closed
5Shift Remarks
Shift Remarks

No Major activity.

1Shift Information
Company Date Shift System
SATCO November 25, 2026 Shift B 3 PM – 11 PM Aerodrome Maintenance
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
17:30 Maintenance GATE 16B – PBB & GPU, MONTHLY PM Schedule Monthly PM/Completed
15:21
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
2434, 2463, 2490 Remove/Replace PBB vinyl flooring, Replace PBB Tire, Fiber optical issue comm. error Remove/Replace PBB vinyl flooring, Replace PBB Tire/Completed, Under IT Dept Overall Shift Lead, Overall Shift Lead, Aerodrome Lead November 26, 2026, November 25, 2026 In Progress, Closed, Open
5Shift Remarks
Shift Remarks

VDGS Stand NR28- Under IT department

1Shift Information
Company Date Shift System
METCO November 24, 2026 Shift B 3 PM – 11 PM Maintenance Common Services
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
16:46 Inspection ////////// /////////////
16:46
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
2278, 2540, 2548, 2549 ctix 4,5 are off due to water leakage, Power outage on Alpha 3, Power outage on Alpha 4, ioscan600 out of service at I/D Drying the machines, electrical team was work on it, electrical team was work on it, Generation and cleaning Shift Lead, Shift Lead, Shift Lead, Shift Lead November 24, 2026, November 24, 2026, November 24, 2026, November 24, 2026 Open, Closed, Closed, Closed
5Shift Remarks
Shift Remarks

All machines working normally just ctix 4&5

1Shift Information
Company Date Shift System
STATION 1 November 24, 2026 Shift B 3 PM – 11 PM Station 1
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
23:00 Maintenance NO MAJOR ACTIVITY N/A
19:30
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
N/A N/A N/A Station 1 Closed
5Shift Remarks
Shift Remarks

NO MAJOR ACTIVITY

1Shift Information
Company Date Shift System
SAFARI November 24, 2026 Shift B 3 PM – 11 PM Airport Electrical System
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
20:09 Inspection none none
20:09
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
NA Monitor ESB-105 project Monitor Electrical lead  November 25, 2026 In Progress
5Shift Remarks
Shift Remarks

ESB-105 Panel replacement work is InProgress

1Shift Information
Company Date Shift System
SATCO November 24, 2026 Shift B 3 PM – 11 PM Aerodrome Maintenance
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
16:00 Inspection N/A N/A
13:29
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
2434 Remove/Replace PBB vinyl flooring Remove/Replace PBB vinyl flooring Overall Shift Lead November 26, 2026 In Progress
5Shift Remarks
Shift Remarks

All equipment’s are working normally

1Shift Information
Company Date Shift System
METCO November 26, 2026 Night Shift (B) 6 PM – 6 AM Aerodrome Maintenance
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
00:00 Inspection //// ///////
21:23
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
2278, 2562, 53525 ctix 4,5 are off due to water leakage, ctix 7 out of service, Power outage on the matrix server room but the system is working normally on UPS Drying the machines, clean the tick sensor and cleaned the detectors and make calibration and put the machine under obeservation, electrical team was work on it Shift Lead, Shift Lead, Electrical lead  November 24, 2026, November 24, 2026 Open, Closed, Open
5Shift Remarks
Shift Remarks

all machine working normal expect ctix 4,5

1Shift Information
Company Date Shift System
SAFARI November 26, 2026 Shift C 11 PM – 7 AM Airport Electrical System
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
00:00 Inspection None None
03:59
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
None None None Electrical lead  Closed
5Shift Remarks
Shift Remarks

Normal

1Shift Information
Company Date Shift System
SAFARI November 25, 2026 Night Shift (B) 6 PM – 6 AM Airport Mechanical System
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
07:00 Maintenance N/A N/A
04:01
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
N/A N/A N/A Mechanical Lead November 25, 2026 Closed
5Shift Remarks
Shift Remarks

N/A

1Shift Information
Company Date Shift System
SATCO November 26, 2026 Shift C 11 PM – 7 AM Aerodrome Maintenance
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
00:00 Maintenance NO MAJOR ACTIVITY N/A
04:02
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
2434, 2490 Remove/Replace PBB vinyl flooring, VDGS NR28-COMMUNICATION ERROR Remove/Replace PBB vinyl flooring, COMMUNICATION ERROR DUE TO FIBER OPTIC – UNDER IT DEPARTMENT Overall Shift Lead, Aerodrome Lead November 26, 2026 In Progress, Open
5Shift Remarks
Shift Remarks

ALL SYSTEM WORKING NORMALLY

1Shift Information
Company Date Shift System
SAFARI November 26, 2026 Shift C 11 PM – 7 AM Airport Terminals & Facilities
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
02:45 Maintenance HDC20 GATE OUT SERVICE ON OPEN POSITION 1000002567
00:45
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
N/A N/A N/A Station 1 Open
5Shift Remarks
Shift Remarks

HDC20 GATE OUT SERVICE ON OPEN POSITION, JOB SCHEDULE ON A SHIFT

1Shift Information
Company Date Shift System
SATCO November 26, 2026 Shift A 7 AM – 3PM PBB Operation & Management
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
13:00 Inspection All PBBs, GPUs & VDGS Daily Inspection Visual Inspection
08:00
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
2434 Gate 23&22 – Remove/Replace PBB vinyl flooring Gate 23&22 – Remove/Replace PBB vinyl flooring Overall Shift Lead November 26, 2026 In Progress
5Shift Remarks
Shift Remarks

All equipment’s are working normally

1Shift Information
Company Date Shift System
SAFARI November 26, 2026 Shift A 7 AM – 3PM Station 1
2Shift Status
Shift Status

EmergencyEmergency

3Operation Logs
Time Category Observation / Action Reference
07:41 Maintenance REPLACED MAIN BREAKER 40000000303
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
40000000303 POWER OUTAGE REPLACED MAIN BREAKER ESB-195 Electrical lead  November 26, 2026 Closed
5Shift Remarks
Shift Remarks

ALVIN-0900H-REPLACED BREAKER WITH
SPARE BREAKER FOR ESB-195 BRANCH OF ESB-125, TRIPPED DUE TO LONG TIME
TRIPPED DELAY.POWER BACK TO NORMAL

1Shift Information
Company Date Shift System
SAFARI November 26, 2026 Shift A 7 AM – 3PM Airport Electrical System
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
13:48 Maintenance none 0000
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
00000 None None Electrical lead  November 26, 2026 Closed
5Shift Remarks
Shift Remarks

No Major activity.

1Shift Information
Company Date Shift System
METCO November 26, 2026 Shift B 3 PM – 11 PM PBSS/HBS
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
00:00 Inspection ////////// ////////////
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
2278, 53525 ctix 4,5 are off due to water leakage, Power outage on the matrix server room but the system is working normally on UPS under obesrvation, still working on it Shift Lead, Shift Lead Closed, Open
5Shift Remarks
Shift Remarks

all machine working fine

1Shift Information
Company Date Shift System
SAFARI November 26, 2026 Day Shift (A) 6 AM – 6 PM Airport Mechanical System
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
19:00 Inspection NA NA
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
NA NA NA Mechanical Lead Closed
5Shift Remarks
Shift Remarks

The systems were operating normally, and no major activities were carried out during the reported date and time.

1Shift Information
Company Date Shift System
SAFARI November 26, 2026 Shift B 3 PM – 11 PM Maintenance Common Services
2Shift Status
Shift Status

EmergencyEmergency

3Operation Logs
Time Category Observation / Action Reference
18:25 Maintenance KONE-DAA00-ELEV-14 PERSON TRAPPED, 1828H-MAHMOOM-PASSENGER RELEASED 40000000321
18:35 Maintenance SAF-UAB00 POWER OUTAGE 40000000304
18:38 Maintenance SAF-UBC00-UIA00-POWER FLUCTUATION, SEE REF 40000000304 1000002580
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
N/A N/A N/A Station 1 Open
5Shift Remarks
Shift Remarks

REF NO. 40000000321 – CLOSED
REF NO. 40000000304 – PENDING
REF NO. 1000002580 – CLOSED

1Shift Information
Company Date Shift System
SAFARI November 26, 2026 Shift B 3 PM – 11 PM Airport Terminal & Facilities
2Shift Status
Shift Status

EmergencyEmergency

3Operation Logs
Time Category Observation / Action Reference
17:00 Maintenance ASD monitoring found door out of hook and out of track/Re hook and re track Log #53678
19:36 Maintenance Admin building room no, G-0343 replace 6pcs busted lights led 16w job completed Log no, 53757
20:16 Maintenance M-0144 there was a leaking hose pipe now replace new one back to normal Log no. 53772
17:20 Inspection water pressure monitoring S12900 due to power outage emergency power outage emergency SAF-UAB00 POWER OUTAGE 40000000304
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
40000000304 International arrival all lights replace any busted lights Facility & Roads Lead November 26, 2026 Open
5Shift Remarks
Shift Remarks

We experienced an emergency, a system power outage at the terminal (arrival, service level1, international departure)

1Shift Information
Company Date Shift System
SAFARI November 26, 2026 Shift B 3 PM – 11 PM Airport Electrical System
2Shift Status
Shift Status

EmergencyEmergency

3Operation Logs
Time Category Observation / Action Reference
06:15 Alert observe power outage in center terminal and north concourse due to tripping MV RMU ESS-3B none
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
None none none Shift Lead November 27, 2026 Closed
5Shift Remarks
Shift Remarks

observe power outage in center terminal and north concourse due to tripping MV RMU ESS-3B .
All power supply back to normal in center terminal and north concourse after restore from MV side.
SWG19 Incomer B open, Tie-1 Close with incomer A
SWG16 Incomer B open Toe-1 close with Incomer A

1Shift Information
Company Date Shift System
SATCO November 26, 2026 Shift B 3 PM – 11 PM PBB Operation & Management
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
16:00 Maintenance N/A N/A
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
2434, 2490, 4000000154 PBB Gate 23/22-Remove/Replace PBB vinyl flooring, VDGS NR 28 – Network comm. error / Fiber optical issue, Power outage affecting VDGS Stands 19–29 and PBBs Gates 19–27. PBB Gate 23/22-Remove/Replace PBB vinyl flooring, Under IT department, Restore power supply to PBBs and VDGS and verify normal operation Overall Shift Lead, Aerodrome Lead, Electrical lead  November 26, 2026 In Progress, Open, Closed
5Shift Remarks
Shift Remarks

All equipment is operating normally, except for VDGS NR28.

1Shift Information
Company Date Shift System
METCO November 27, 2026 Night Shift (B) 6 PM – 6 AM PBSS/HBS
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
02:00 Maintenance WE JEST CLEANING TEH FANS CHECKING THE POWER WORKING NORMAL /////////////
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
53525 Power outage on the matrix server room but the system is working normally on Electrical lead Electrical lead  Open
5Shift Remarks
Shift Remarks

ALL MACHINES WORKING NORMALLY

1Shift Information
Company Date Shift System
SAFARI November 27, 2026 Shift C 11 PM – 7 AM Maintenance Common Services
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
07:00 Maintenance NO MAJOR ACTIVITY REPORTED N/A
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
N/A N/A N/A Station 1 Closed
5Shift Remarks
Shift Remarks

NO MAJOR ACTIVITY REPORTED

1Shift Information
Company Date Shift System
SATCO November 26, 2026 Shift C 11 PM – 7 AM PBB Operation & Management
2Shift Status
Shift Status

NormalNormal

3Operation Logs
Time Category Observation / Action Reference
00:00 Maintenance N/A N/A
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
2434, 2490 PBB Gate 23/22-Remove/Replace PBB vinyl flooring, VDGS NR 28 – Network comm. error / Fiber optical issue Remove/Replace PBB vinyl flooring Overall Shift Lead In Progress
5Shift Remarks
Shift Remarks

All equipment’s are working normally

1Shift Information
Company Date Shift System
SAFARI November 27, 2026 Shift C 11 PM – 7 AM Airport Electrical System
2Shift Status
Shift Status

AlertAlert

3Operation Logs
Time Category Observation / Action Reference
03:50 Maintenance Breaker reset at AEB-04 53780 log
4Outstanding Alerts / Actions
Related Log Issue / Alert Target Date Required Action Responsible Status
None No supply at CARGO AREAS Engage energia to install generator Electrical lead  In Progress
5Shift Remarks
Shift Remarks

Rest of the system normal. Need dual supply sourse for cargo area as existing facilities generator not working